Remodel Expense Tracker
Full remodel · all vendors paid from Wells Fargo checking …2227 • Statements through June 30, 2026 • Updated July 9, 2026
How far into the $750,000 budget the project is after two months of work.
Net spend by vendor and purpose, May 11 – June 30.
Net project cost per statement month.
May was mostly mold remediation and plans; June was the first big contractor payment. New months are added as each statement arrives.
Every transaction from the bank statements, oldest first. Grayed rows are the failed wire that was returned — only the $45 the banks kept counts as spend.
| Date | Paid to / Description | Category | Amount | Account Balance |
|---|---|---|---|---|
| May 2026 | ||||
| May 11 | Initial funding Branch deposit, Fort Collins CO | Funding | +250,000.00 | 250,000.00 |
| May 14 | Tristan Villanueva Zelle — memo “Plans” | Plans & Design | −3,000.00 | 247,000.00 |
| May 26 | Adrian Paris Zelle sent 5/24 — memo “Mold” | Mold Remediation | −5,000.00 | 242,000.00 |
| May 26 | Adrian Paris Zelle sent 5/25 — memo “Mold” | Mold Remediation | −5,000.00 | 237,000.00 |
| May 27 | Adrian Paris Check #101 | Mold Remediation | −10,000.00 | 227,000.00 |
| May 27 | Adrian Paris Zelle — memo “Mold” | Mold Remediation | −2,559.00 | 224,441.00 |
| May 29 | Interest payment | Interest | +1.32 | 224,442.32 |
| June 2026 | ||||
| Jun 5 | Wire to David Lazcano via Bank of America — returned 6/8, did not go through | General Contractor | −80,000.00 | 144,442.32 |
| Jun 8 | Wire returned $45 kept by banks in transit — counted under Fees | General Contractor | +79,955.00 | 224,397.32 |
| Jun 11 | Wire transfer service charge | Bank & Wire Fees | −40.00 | 224,357.32 |
| Jun 11 | Wire to David Lazcano via Bank of America — cleared | General Contractor | −80,000.00 | 144,357.32 |
| Jun 24 | David Lazcano Check #105 | General Contractor | −15,000.00 | 129,357.32 |
| Jun 30 | Interest payment | Interest | +1.31 | 129,358.63 |